Move visits on the Gantt chart by dragging it to
a new time slot.
When you move visits on the Gantt chart, the due dates of subsequent repeating or chained tasks are automatically updated. 
You can also move a visits by typing new start and end dates. 
-  Click Menu 
, and then click Plan management.  
- Click the plan you want to view.
 
- Click Edit.
 
- Click the visit you want to move.
               Tip: Do either of the following:
                  
- 
                        
To multi-select individual visits on the same track, hold down the CTRL key, and then click the individual visits you want to move. 
                      
- 
                        
To multi-select a series of visits on the same track, hold down the SHIFT key, then click on each of the visits you want to move.
 
Locked visits cannot be multi-selected.
 
 
              
- Drag the visit(s) to a new position.
               
               
                  Note: 
                     - If moving a visits forces one of its tasks to become overdue, the
					visit is displayed in red to highlight its overdue status.
 
- 
                           
If a visit is moved to a time slot that overlaps with another visit, the other visit will be bumped. 
                         
- 
                           
Visit spans will change if there are differences in non-working days.