One-time tasks

A one-time task is a task that occurs only once.

These tasks are defined in the Task Definition operational data. The Chained Tasks, Repeat Days, Repeat Hours and Repeat Cycles fields should be blank.

To define a one-time task, provide at least one of the following:
  • Initial Hours

  • Initial Days

  • Initial Cycles

  • Due Date

They may terminate other tasks.

One-time task definition example
Task Id Name Chained Tasks Description Schedule Calculation From Type
FC11 C11   One-time task EARLIEST EFFECTIVE_

DATE
CHECK
One-time task definition example (continued)
Effective Date Effective Hours Effective Cycles Initial Days Initial Hours Initial Cycles
2017-08-01     121    
One-time task definition example (continued)
Repeat Days Repeat Hours Repeat Cycles Due Date FIS Spec FIS Value Min Yield
FC11 C11   One-time task EARLIEST EFFECTIVE_

DATE
0.8
One-time task definition example (continued)
Max Yield Span Terminating Days Terminating Usage Hours Terminating Usage Cycles Terminating Task Scheduled by EOM
1 5         FALSE